NGTL System - Pricing & Tolls

NGTL System Transportation Rates & Abandonment Surcharge

 

Preliminary 2024 Interim Rates and Abandonment Surcharge
(Proposed Effective January 1
, 2024)

 

2023 Final Rates - Effective June 1, 2023

Receipt and delivery transportation Rates below do not include applicable abandonment surcharges.

 

Receipt Services

 

Tariff Rate

 

Information Purposes

   

$/10³m³ (Cdn)

 

¢/GJ/d (Cdn)

¢/Mcf/d (Cdn)

¢/MMBtu/d (US)

FT-R Average Demand Rate (3 yr term) 1  

283.02 /mo

 

24.6

26.4

19.7

IT-R (Interruptible Receipt)   10.70 /d  

28.3

30.3

22.7

 

Delivery Services

 

Tariff Rate

 

Information Purposes

   

$/GJ (Cdn)

 

¢/GJ/d (Cdn)

¢/Mcf/d (Cdn)

¢/MMBtu/d (US)

FT-D Demand Rate (1 yr term) 2            
Group 1:            

     Empress/McNeill Border

  5.95 /mo   19.6 20.9 15.7
     Alberta-B.C. Border  

6.61 /mo

 

21.7 23.3 17.4
     Gordondale Border  

5.95 /mo

  19.6 20.9 15.7
     ATCO: Clairmont/Shell Creek/Edson  

5.95 /mo

  19.6 20.9 15.7
Group 2:            
     All Group 2 delivery points  

8.37 /mo

  27.5 29.5 22.1
Group 3:            
     All Group 3 delivery points   10.05 /mo   33.0 35.4 26.5
             
IT-D (Interruptible Delivery)            
Group 1:  

 

 

 

 

 

     Empress/McNeill Border    

 

21.51 23.03 17.2
     Alberta-B.C. Border    

 

23.91 25.61 19.2
     Gordondale Border    

 

21.51 23.03 17.2
     ATCO: Clairmont/Shell Creek/Edson    

 

21.51 23.03 17.2
Group 2:  

 

 

 

 

 

     All Group 2 delivery points  

 

 

30.28 32.42 24.3

 

1More details on Receipt Price Points at Receipt Point Rates                 2 More details on Delivery Price Points at Delivery Point Rates
1-2 year term: 105% (Price Point C)                                                                          1-2 year term: 100% (Price Point Z)
3-4 year term: 100% (Price Point B)                                                                          3-4 year term: 95% (Price Point Y)
5+ year term: 95% (Price Point A)                                                                              5+ year term: 90% (Price Point X)

- Aggregate charges for service will be determined in accordance with the NGTL System tariff and as such, shall include the applicable abandonment surcharge(s).
- Rates are payable in Canadian dollars.
- For billing purposes,10³m³ units are used to Receipt Services and GJ units are for Delivery services.
- Mcf and MMBtu units are provided for illustrative purposes only.
- Conversion factors below have been used to calculate the rates provided for information purposes:

  Cdn$/US$ 1.32 - subject to change (updated Sept 14, 2022)
  ¢/GJ to ¢/MMBtu 1.06
  $/10³m³ to ¢/GJ 37.8 MJ/m³

- Actual heating value is dependent upon specific receipt or delivery points and ranges from 36.0 MJ/m3 to 44.0 MJ/m3.
- Rates do not include GST.
- FT-R rate range (3 yr term):

  FT-R Rate Range $/103m3 ¢/GJ/d ¢/Mcf/d ¢/MMBtu/d
  FT-R Floor Rate 127.71 /mo 11.1 11.9 8.9
  FT-R Ceiling Rate 460.69 /mo 40.1 42.9 32.1

 

2023 Final Abandonment Surcharges - Effective January 1, 2023

Abandonment surcharges are in addition to applicable receipt and delivery transportation rates.

 

Abandonment Surcharges

Tariff Rate

Information Purposes

 

 

$/10³m³ (Cdn)

$/GJ(Cdn)

$/Mcf (Cdn)

 

Monthly Abandonment Surcharge

6.94 /mo

0.18 /mo

0.2 /mo

 

Daily Abandonment Surcharge

0.23 /d

0.0060 /d

0.01 /d

- The services to which abandonment surcharges apply are denoted on the NGTL Tariff Table of Rates, Tolls and Charges.

 

Other information for TC Energy's NGTL System:

 Current

Archives

 Receipt Point Rates NGTL Archived Rates
 Delivery Point Rates Fuel Rates (2004 - 2010) (22 KB, XLS)
 Fuel Rates Fuel Rates (2000 - 2004) (41 KB, DOC)
 AB Border Heat Values AB Border Heat Values (61 KB, PDF)

 

Disclaimer:

The pricing and tolls information included on this website is intended to be used for planning purposes only and although TC Energy endeavours to maintain the information in such a way that is accurate and current, it may not provide accurate results. Use of this information is at user’s sole risk and TC Energy shall not be liable for user’s use or reliance on any results obtained from it.